Loan types · 7 min read

How Commercial Construction Loans Work

Short answer

A commercial construction loan funds a building project in stages. The lender commits to a total amount, you put your equity in first, and the loan is then advanced in draws as work is completed and inspected. You pay interest only on what has been drawn, usually at a floating rate, and repay the loan by selling the finished property or refinancing into permanent debt.

An apartment building under construction
An apartment building under construction. Example photo: 4300streetcar, CC BY 4.0, via Wikimedia Commons.

How a construction loan differs from other commercial loans

A permanent lender underwrites a building that exists and income that is already coming in. A construction lender has neither. It is lending against a set of plans, a budget, a builder and your ability to finish. That is why construction loans are shorter, more closely monitored and more often guaranteed than other commercial loans.

  • Term: commonly 18 to 36 months, sized to the construction schedule plus time to lease up or sell, often with extension options.
  • Rate: usually floating, an index plus a spread, with interest-only payments.
  • Funding: advanced in draws, not in one lump sum at closing.
  • Recourse: banks commonly require a repayment guaranty and a completion guaranty. See recourse vs. non-recourse loans.
  • Lenders: mostly banks, plus debt funds and private lenders for higher-risk or higher-proceeds deals.

Two government programs work differently. HUD's 221(d)(4) combines construction and permanent financing for apartments (see HUD multifamily loans), and SBA loans can fund a building for your own business (see SBA 504 vs. 7(a)).

How lenders size a construction loan

The main test is loan-to-cost: the loan as a share of the total project budget. Banks commonly lend about 60% to 75% of cost. The lender also checks loan-to-value against the appraised value of the completed, stabilized property, and whether the finished building's income will support a permanent loan large enough to repay the construction loan. LTV vs. LTC explains how the two measures differ.

A hypothetical example. Land costs $3 million, hard costs are $13 million, soft costs are $3 million and financing costs with an interest reserve are $1 million. Total budget: $20 million. At 65% of cost the loan is $13 million and you need $7 million of equity. If the appraiser values the finished, leased property at $26 million, the loan is 50% of that value. If stabilized NOI is projected at $1.6 million, the debt yield on the construction loan is about 12.3%, which gives a permanent lender room to refinance it.

Land you already own can usually count toward your equity. Whether it counts at what you paid or at its current appraised value varies by lender, so ask early.

The budget the lender approves

The loan is built on a line-item budget. Once the lender approves it, moving money between lines usually needs consent.

Budget categoryWhat it covers
LandPurchase price or agreed value of the site
Hard costsSite work, materials, labor, the contractor's fee
Soft costsDesign, engineering, permits, legal, insurance, taxes during construction
Financing costsLoan fees, title, third-party reports, interest reserve
ContingencyA cushion for overruns, commonly about 5% to 10% of hard costs

The interest reserve is a part of the loan set aside to pay the loan's own interest during construction and lease-up, when the property has no income. Each month the lender draws on the reserve to make the payment. If construction runs long or the rate rises, the reserve can run out, and you then pay interest from your own cash.

Lenders also require the loan to stay in balance. If the cost to finish ever exceeds the undrawn loan plus remaining equity, you must deposit the difference before the lender funds another draw.

How the draw process works

Most lenders require your equity to go into the project first. After that, draws usually follow a monthly cycle.

  1. The contractor submits a payment application showing the work completed against each line of the budget.
  2. You submit a draw request with invoices for soft costs and any change orders.
  3. The lender's inspector or construction consultant visits the site and confirms the work is in place.
  4. The title company updates the title search, and lien waivers are collected from the contractor and subcontractors.
  5. The lender funds the draw, less retainage.

Retainage is a portion of each payment to the contractor, commonly 5% to 10%, that is held back until the work is substantially complete. It gives the contractor a reason to finish and gives the lender a cushion. Plan your cash around the cycle, because the time from request to funding can stretch if paperwork is missing. Change orders above a set size typically need lender approval before the work is done.

What a construction lender wants before closing

  • Entitlements and permits: zoning in place and building permits issued or ready to issue.
  • Plans and a contract: complete drawings and a signed construction contract, often with a guaranteed maximum price, from a contractor with relevant experience.
  • A reviewed budget and schedule: the lender's own consultant checks that the cost and timeline are realistic.
  • Sponsor strength: a track record with similar projects, plus net worth and liquidity to cover overruns.
  • Market support: an appraisal and often a market study. For office, retail and condominiums, lenders commonly want pre-leasing or presales.
  • Site reports: environmental and soil reports, and a survey.
  • Guarantees: completion, repayment (sometimes reduced as milestones are met) and often a guaranty of carrying costs.

A complete package gets a faster and better answer. How to find a construction lender covers which lenders to approach and in what order.

The exit: sale, refinance or mini-perm

A construction loan is repaid in one of three ways. You sell the finished property. You refinance with a permanent loan once the building is leased and meets the new lender's occupancy and DSCR tests. Or the construction loan itself converts into a short permanent phase, often called a mini-perm, that gives you a few more years with amortizing payments.

The gap between completion and stabilization is where projects get squeezed. The construction loan is near maturity, the building is not yet full and a permanent lender will not lend on projected rents. Extension options and a bridge loan for the lease-up period are the usual answers. Check the extension conditions at the start, because they often require a completed building and a minimum level of leasing.

Terms and guaranty requirements vary widely by lender and project, so confirm them with the lender and your own counsel before you commit.

Where CREaiD helps

Construction lending is local and selective. Lenders differ on project size, property type, market and how much of the cost they will fund.

In CREaiD's Lender Matchmaker you describe the project and get lenders that fit from a database of 1,500+ commercial real estate lenders, including banks, credit unions, private lenders and private equity. You can also upload deal data for a quick investment analysis before you go to market.

Brian Gramlich
About the author

Brian Gramlich is the CEO and founder of Terrydale Capital, a commercial real estate finance firm based in Dallas, Texas, and the founder of CREaiD.

Key takeaways

  • A construction loan is committed up front and funded in draws as work is completed and inspected.
  • Lenders size it mainly on loan-to-cost, then check completed value and the takeout.
  • Your equity usually goes in first, and the loan must stay in balance with the cost to finish.
  • Expect a floating rate, an interest reserve, retainage and completion and repayment guaranties.
  • Plan the period between completion and stabilization before you close.

Questions people ask

How much equity do I need for a construction loan?

With bank loans commonly at about 60% to 75% of cost, plan on 25% to 40% of the total budget in equity. Land you already own can usually count toward it. Higher loan amounts are available from debt funds and private lenders, at a higher price.

Are construction loans recourse?

Usually, yes. Banks commonly require a repayment guaranty and a completion guaranty from the sponsor. Some lenders reduce the repayment guaranty once the building is finished or reaches a set level of leasing, and non-recourse construction debt exists for strong sponsors at lower loan amounts.

What is an interest reserve?

It is a line in the loan budget used to pay the loan's own interest while the property has no income. The lender advances from it each month. It is sized on an estimate of draws, timing and rates, so delays or higher rates can use it up early.

What is a construction-to-permanent loan?

It is a single loan that covers construction and then converts to a longer amortizing loan without a new closing. Banks offer it as a mini-perm, and HUD's 221(d)(4) program offers a long-term version for apartments. It removes the need to find a separate takeout at completion.

What happens if the project goes over budget?

The contingency is used first. If the overrun is larger, the loan is out of balance and you must put in more cash before the lender funds further draws. This is why lenders look closely at your liquidity and at the completion guaranty.